Legacy Community Recreation Education and Wellness Building funded by the community of Woodbine, Woodbine Schools, and Mary and Todd Heistand.
This project had an approximate design timeline of 6 months, with construction to substantial completion of 9 months. Construction start in late March / early April 2020, at the beginning of the great COVID shut-down.
Regulation pool for high school swim competition placed within a sprung structure, connecting to a main structure (full gymnasium) composed of steel scissor-trusses supported by precast concrete panels. Ancillary additions and infill housing a senior center, registered child care center, and a variety of meeting and education rooms are all comprised of light-gauge steel construction.
This building served as a stepping stone to a fairly large expansion of Woodbine, being adjacent to the envisioned Harvest Hills subdivision as well as the IGNITE Pathways STEAM center (open for students fall 2023) for the high school.